how we got here
CES ⇒ Condition Survey ⇒ document development ⇒ 2015 exterior restoration project ⇒ construction management ⇒ ces renewal
$120 K
project total cost
5 months
project duration
management firm
contractor
General project scope:
- Demolition Existing Decking
- Replace Boardwalk
- Replace Handrails
- Stucco Repairs
- Install CMU Foundation
- Painting
before